Permits in Sanibel.
Sanibel is almost entirely barrier island and still in active post-Ian reconstruction. It also runs a two-step review that catches out contractors used to a single building review.
What is different about Sanibel
- Planning Division review is required before Building Division review for new construction and structural exterior modifications. That is two sequential reviews, not one.
- The city moved to a new permitting portal on March 31, 2026, replacing its previous system.
- The island remains in documented post-hurricane reconstruction, and the city maintains dedicated recovery guidance alongside its normal permitting pages.
Review times
The city states an initial review within seven to ten business days, with up to 30 days for a complete evaluation once a full submission is received.
Review times, fee schedules, forms and portals change, sometimes on a specific effective date. Everything on this page was verified on September 1, 2026. Confirm anything load-bearing with the department before you rely on it.